Description
A new design concept has transformed the station’s appearance
Even whilst the station’s reconstruction project was still in the planning stages, Dopravní podnik hl.m. Prahy a.s. launched a design competition for the future appearance of Českomoravská station. The designer of the winning entry subsequently worked with the station’s refurbishment architects to devise the final design for the station itself, as well as for the escalator tunnel and the public area of the concourse. The station itself has undergone the most significant transformation. The ceramic tiles were removed and replaced with large-format glass tiles, both behind the tracks and on the platform. To create greater contrast, the designers complemented the large-format tiles on the platform with stainless steel panels in the flat sections. This theme continues into the escalator tunnel, where it flows seamlessly into the stainless steel balustrades of the new escalators. The cladding on the vaults, both in the station and in the escalator tunnel, remains in white enamelled sheet metal. The whole project is complemented by the installation of new lighting with a pleasant intensity and colour temperature.
A unique renovation of the platform and structural elements
As early as 2016, Pontex s.r.o. carried out a diagnostic survey in which it highlighted the critical condition of the platform’s steel cross-beams. The structural analysis section of the project documentation addresses this issue in great detail, and a complete replacement of the platform slab in the central bay has been proposed. This proposal is unique and has not been implemented in any Prague Metro stations to date.
Other activities relating to the station’s refurbishment were of a more conventional nature. From a structural perspective, this involved the rehabilitation of the lining along the entire length of the station and the adjacent track sections. Within the station itself, the service tunnel, the escalator tunnel and the vestibule, the work consisted of ancillary tasks associated with the replacement of technical equipment and minor layout adjustments.
Comprehensive modernisation of technical equipment
From a technical perspective, the reconstruction included the replacement of the escalators leading from the platform to the concourse, as well as the complete replacement of both standard and emergency lighting, including the control system. The station’s ventilation system and power distribution systems, including switchboards, were also refurbished. The previously modernised fire alarm system was upgraded. The refurbishment also included a complete set of new low-voltage equipment, including terminal devices. The modernisation of the relevant control systems was carried out in conjunction with the new ventilation and lighting technology.